Rugby Canada High Performance Training Centre
Federal contribution
$2.9M
$2,935,250
Federal share46%
of $6.3M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 31, 2015
ApprovedMay 16, 2016
201620172018
Built
Approved 10 months after the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- City of Langford
- Construction start
- Nov 1, 2016(actual)
- Construction end
- Dec 21, 2017(actual)
Against the original forecast
- Construction start2 months lateforecast Sep 1, 2016
- Construction end6 weeks earlyforecast Jan 31, 2018
Also in Langford