Protective Flood Disaster Mitigation Works - Millbrook

Otonabee-South Monaghan, Ontario

completeDisaster MitigationSCF
Federal contribution
$1.1M
$1,119,167
Federal share33%

of $3.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 3, 2015
2016201720182019
Built

Approved 2 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Jan 18, 2018(actual)
Construction end
Sep 30, 2019(actual)

Against the original forecast

  • Construction start4 months lateforecast Sep 30, 2017
  • Construction end2 months earlyforecast Nov 29, 2019