Keene Heights water treatment plant Supervisory Control & Data Acquisition (SCADA) System Replacement and Upgrade
Otonabee-South Monaghan, Ontario
Federal contribution
$17,250
Federal share50%
of $34.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2017
2018
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Otonabee-South Monaghan
- Construction start
- Feb 22, 2017(actual)
- Construction end
- Aug 31, 2018(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Apr 1, 2017
- Construction end5 months lateforecast Mar 31, 2018
Also in Otonabee-South Monaghan
- Protective Flood Disaster Mitigation Works - Millbrook$1.1M
- Watermain Upgrade in Crystal Springs Subdivision$483.5K
- Otanabee Memorial Community Centre Dehumidifier Replacement$80.0K
- Elgeti/Stewart Hall/Crystal Springs Supervisory Control and Data Acquisition (SCADA) System Replacement and Upgrade including Process Controller, Targeting and Monitoring System$25.9K
- Keene Water Treatment Plant (WTP) Energy Efficiency Upgrades to Heating, Insulation and Lighting Systems$2.3K