Back to projects

Elgeti/Stewart Hall/Crystal Springs Supervisory Control and Data Acquisition (SCADA) System Replacement and Upgrade including Process Controller, Targeting and Monitoring System

Otonabee-South Monaghan, Ontario

completeDrinking WaterCWWF
Federal contribution
$25,875
Federal share50%

of $51.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2017
2018
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
May 24, 2017(actual)
Construction end
Aug 31, 2018(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Apr 1, 2017
  • Construction end5 months lateforecast Mar 31, 2018

Also in Otonabee-South Monaghan