Emily St. watermain and sanitary sewer upgrades
Federal contribution
$762,600
Federal share33%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 7, 2015
2016201720182019
Built
Approved 7 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Parry Sound
- Construction start
- Sep 1, 2016(actual)
- Construction end
- Jan 28, 2019(actual)
Against the original forecast
- Construction start4 months lateforecast May 2, 2016
- Construction end7 months lateforecast Jun 29, 2018
Also in Parry Sound
- Highway 69 Project; Four-Lane Expansion from Highway 529 to Highway 522$120.0M
- Highway 69 Project; 4-Lane Expansion, Highway 559 Northerly$49.3M
- West Parry Sound Area Recreation and Culture Centre joint project between 7 Municipalities and 2 First Nations Communities$12.8M
- Upgrading of Parry Sound Wastewater Treatment Plant$5.3M
- Highway 518 - East of Highway 400 towards Orrville$2.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46194 in the federal list. How to read these figures.