Back to projects

Trenton Wastewater Treatment Plant Headworks Upgrades

Quinte West, Ontario

completeWastewaterSCF
Federal contribution
$1.9M
$1,872,384
Federal share33%

of $5.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 26, 2015
201620172018
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Quinte West
Construction start
Jul 8, 2015(actual)
Construction end
Mar 2, 2018(actual)

Against the original forecast

  • Construction start3 months earlyforecast Oct 21, 2015
  • Construction end4 weeks earlyforecast Mar 31, 2018

Also in Quinte West

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46196 in the federal list. How to read these figures.