Waterfront Trail Extension

Quinte West, Ontario

underwayActive TransportationATF
Federal contribution
$2.2M
$2,160,000
Federal share60%

of $3.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 1, 2025
today
20232024202520262027
BuiltForecast

Approved 2.9 years before the announcement.

Program
Active Transportation Fund
Ultimate recipient
City of Quinte West
Construction start
Sep 30, 2025(actual)
Construction end
Jan 31, 2027(forecast)

Against the original forecast

  • Construction start16 months lateforecast Jun 1, 2024

Also in Quinte West

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63544 in the federal list. How to read these figures.