Rehabilitation of Shuter Street and Lorne Avenue Watermains
Federal contribution
$1.1M
$1,139,500
Federal share40%
of $2.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2022
2023
Built
Approved 6 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Quinte West
- Construction start
- Jun 6, 2022(actual)
- Construction end
- Dec 19, 2022(actual)
Against the original forecast
- Construction end3 weeks lateforecast Nov 30, 2022
Also in Quinte West
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62870 in the federal list. How to read these figures.