Rehabilitation of Shuter Street and Lorne Avenue Watermains

Quinte West, Ontario

completeDrinking WaterGIS
Federal contribution
$1.1M
$1,139,500
Federal share40%

of $2.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2022
2023
Built

Approved 6 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Quinte West
Construction start
Jun 6, 2022(actual)
Construction end
Dec 19, 2022(actual)

Against the original forecast

  • Construction end3 weeks lateforecast Nov 30, 2022