Foster Avenue Reconstruction
Federal contribution
$238,381
Federal share33%
of $715.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2015
2016
Built
Approved 8 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Smiths Falls
- Construction start
- Aug 22, 2016(actual)
- Construction end
- Nov 18, 2016(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 20, 2016
- Construction end3 months lateforecast Sep 1, 2016
Also in Smiths Falls
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46224 in the federal list. How to read these figures.