Regional Waterline Expansion Diversion East
Federal contribution
$900,000
Federal share33%
of $2.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 31, 2015
20162017
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Portage La Prairie
- Construction start
- Mar 3, 2016(actual)
- Construction end
- Dec 16, 2016(actual)
Against the original forecast
- Construction start4 weeks lateforecast Feb 1, 2016
- Construction end3 weeks lateforecast Nov 25, 2016
Also in Portage la Prairie
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46323 in the federal list. How to read these figures.