Water Distribution Plant and Reservoir
Federal contribution
$1.4M
$1,450,000
Federal share33%
of $4.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 31, 2015
201620172018
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Humboldt
- Construction start
- Apr 18, 2016(actual)
- Construction end
- Mar 29, 2018(actual)
Against the original forecast
- Construction start3 weeks lateforecast Mar 31, 2016
Also in Humboldt
- City of Humboldt - Wastewater Treatment System Upgrades$14.7M
- Uniplex and High School Retrofit$973.2K
- City of Humboldt Storm Water Detention Pond$647.1K
- Regional Authority of Carlton Trail Waste Management District (REACT) - Phase 2 Decommissioning of REACT Waste Management Facility$583.8K
- REACT - Decommissioning of Non-engineered Four Remaining Cells of the Transfer Station of Humboldt$379.8K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46351 in the federal list. How to read these figures.