Back to projects

Regional Authority of Carlton Trail Waste Management District (REACT) - Phase 2 Decommissioning of REACT Waste Management Facility

Humboldt, Saskatchewan

approvedSolid Waste ManagementGIS
Federal contribution
$583,764
Federal share40%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 27, 2022
today
202220232024202520262027
BuiltForecast

Approved 3 months before the announcement.

Program
Green Infrastructure Stream
Construction start
May 19, 2026(forecast)
Construction end
Mar 31, 2027(forecast)