Back to projects

City of Humboldt - Wastewater Treatment System Upgrades

Humboldt, Saskatchewan

underwayWastewaterGIS
Federal contribution
$14.7M
$14,733,561
Federal share40%

of $36.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 23, 2021
today
2021202320252027
BuiltForecast

Approved 9 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Humboldt
Construction start
Mar 11, 2024(actual)
Construction end
Oct 31, 2026(forecast)

Also in Humboldt