Fauquier Water Treatment Plant Upgrades

Fauquier-Strickland, Ontario

completeDrinking WaterSCF
Federal contribution
$878,578
Federal share33%

of $2.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 18, 2016
2016201820202022
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
May 3, 2021(actual)
Construction end
Jul 21, 2022(actual)

Against the original forecast

  • Construction start2.3 years lateforecast Jan 7, 2019
  • Construction end5 months earlyforecast Dec 31, 2022