Back to projects

Renovations and retrofits of the Municipal Offices

Fauquier-Strickland, Ontario

completeVentilationCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 7, 2021
2022
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Mar 1, 2022(actual)
Construction end
Aug 5, 2022(actual)

Against the original forecast

  • Construction start3 months earlyforecast Jun 6, 2022
  • Construction end8 weeks earlyforecast Sep 30, 2022

Also in Fauquier-Strickland