Replace existing 8.5 HP raw water low lift pump
Federal contribution
$8,105
Federal share50%
of $16.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
2018
Built
Approved 2 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Fauquier-Strickland
- Construction start
- Oct 10, 2017(actual)
- Construction end
- Nov 30, 2018(actual)
Against the original forecast
- Construction start7 months lateforecast Mar 6, 2017
- Construction end7 months lateforecast Apr 30, 2018
Also in Fauquier-Strickland
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48648 in the federal list. How to read these figures.