completeSolid Waste ManagementSCF
Federal contribution
$250,328
Federal share33%

of $751.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 18, 2016
20162017201820192020
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Sep 24, 2016(actual)
Construction end
Oct 16, 2020(actual)

Against the original forecast

  • Construction start3 months lateforecast Jul 1, 2016
  • Construction end6 weeks earlyforecast Nov 30, 2020