Safety Retrofit of Municipal Public Works Building
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 7, 2021
2022
Built
Approved 2 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Municipality of French River
- Construction start
- Nov 8, 2021(actual)
- Construction end
- Jan 31, 2022(actual)
Also in French River
- Rehabilitation of Shaw Road$500.0K
- Rehabilitation and Renovation of the Alban Community Centre$438.7K
- Noelville Landfill Improvement Program$250.3K
- District 11 - Project 2 - Near North Trails Association - Round Nippissing Tour Improvement$210.8K
- Assessment of Noelville Wastewater/Stormwater Infrastructure Upgrades$50.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59716 in the federal list. How to read these figures.