Back to projects

Safety Retrofit of Municipal Public Works Building

French River, Ontario

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 7, 2021
2022
Built

Approved 2 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Nov 8, 2021(actual)
Construction end
Jan 31, 2022(actual)

Also in French River

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59716 in the federal list. How to read these figures.