Rehabilitation and Renovation of the Alban Community Centre

French River, Ontario

underwayOtherCCRIS
Federal contribution
$438,720
Federal share40%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 19, 2021
today
2021202320252027
BuiltForecast

Approved 2 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Construction start
Apr 4, 2022(actual)
Construction end
Dec 31, 2026(forecast)