Back to projects

Serpent River Landfill Site Cell Capping

Sault Ste. Marie, Ontario

underwaySolid Waste ManagementSCF
Federal contribution
$292,125
Federal share33%

of $876.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 18, 2016
201620182020202220242026
BuiltForecast

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Township of The North Shore
Construction start
Jan 10, 2018(actual)
Construction end
Sep 15, 2025(forecast)

Against the original forecast

  • Construction start7 months earlyforecast Aug 1, 2018