Trans-Canada Highway 1 - Donald to Forde Station Road Four-Laning

Golden, British Columbia

completeHighways and RoadsNRP
Federal contribution
$7.0M
$7,003,412
Federal share48%

of $14.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 17, 2017
201720182019
Built

Approved 2 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Apr 17, 2018(actual)
Construction end
Sep 15, 2019(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Apr 1, 2018
  • Construction end7 weeks lateforecast Jul 31, 2019

Also in Golden

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46557 in the federal list. How to read these figures.