Estevan Residuals Management Facility and Source Water Intake
Federal contribution
$3.1M
$3,133,333
Federal share33%
of $9.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 10, 2016
2017201820192020
Built
Approved 7 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- City of Estevan
- Construction start
- Jun 1, 2017(actual)
- Construction end
- Oct 30, 2020(actual)
Against the original forecast
- Construction start2 weeks lateforecast May 15, 2017
- Construction end4 months lateforecast Jun 30, 2020
Also in Estevan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46571 in the federal list. How to read these figures.