City of Estevan - Pedestrian Corridor Expansion
Federal contribution
$1.5M
$1,517,600
Federal share40%
of $3.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 6, 2021
2022
Built
Approved 7 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Estevan
- Construction start
- Jul 26, 2021(actual)
- Construction end
- Dec 31, 2021(actual)
Against the original forecast
- Construction start4 months lateforecast Apr 1, 2021
- Construction end6 months earlyforecast Jun 30, 2022