Back to projects

City of Estevan - Leisure Centre Rooftop and HVAC Rehabilitation

Estevan, Saskatchewan

completeRecreationRNIS
Federal contribution
$542,094
Federal share40%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 25, 2023
20232024
Built

Approved 2 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
City of Estevan
Construction start
Sep 30, 2023(actual)
Construction end
Jul 17, 2024(actual)

Against the original forecast

  • Construction start4 months lateforecast May 31, 2023
  • Construction end2 weeks lateforecast Jun 30, 2024

Also in Estevan

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65310 in the federal list. How to read these figures.