City of Estevan - Leisure Centre Rooftop and HVAC Rehabilitation
Federal contribution
$542,094
Federal share40%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 25, 2023
20232024
Built
Approved 2 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- City of Estevan
- Construction start
- Sep 30, 2023(actual)
- Construction end
- Jul 17, 2024(actual)
Against the original forecast
- Construction start4 months lateforecast May 31, 2023
- Construction end2 weeks lateforecast Jun 30, 2024