Teslin Drainage and Road Upgrades

Teslin, Yukon

completeHighways and RoadsSCF
Federal contribution
$825,000
Federal share75%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 18, 2016
201720182019
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Village of Teslin
Construction start
Oct 1, 2016(actual)
Construction end
Nov 30, 2018(actual)

Against the original forecast

  • Construction start5 months lateforecast May 1, 2016
  • Construction end6 months earlyforecast May 31, 2019

Also in Teslin

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46600 in the federal list. How to read these figures.