Water System/Road Upgrade, Island Pond Road, Phase 2
Kippens, Newfoundland and Labrador
Federal contribution
$90,796
Federal share33%
of $272.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 20, 2016
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Kippen
- Construction start
- Jun 21, 2016(actual)
- Construction end
- Sep 22, 2016(actual)
Against the original forecast
- Construction start5 weeks lateforecast May 15, 2016
- Construction end13 months earlyforecast Oct 31, 2017
Also in Kippens
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46668 in the federal list. How to read these figures.