McCarthy's Lane Storm Sewer
Kippens, Newfoundland and Labrador
Federal contribution
$269,000
Federal share33%
of $807.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 10, 2018
2019
Built
Approved 3 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Kippens
- Construction start
- Aug 19, 2019(actual)
- Construction end
- Oct 13, 2019(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jun 30, 2019
- Construction end5 weeks earlyforecast Nov 15, 2019
Also in Kippens
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52243 in the federal list. How to read these figures.