Road Upgrading - Island Pond Drive - Phase 3

Kippens, Newfoundland and Labrador

completeWastewaterSCF
Federal contribution
$230,910
Federal share24%

of $982.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 1, 2017
2018
Built

Approved 2 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Kippens
Construction start
Jul 23, 2018(actual)
Construction end
Nov 14, 2018(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Jul 9, 2018
  • Construction end12 months earlyforecast Nov 14, 2019