Rehabilitation of the Buffalo River Bridge on Highway 5
Fort Smith, Northwest Territories
Federal contribution
$8.1M
$8,062,500
Federal share75%
of $10.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
20172018
Built
Approved 8 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Government of Northwest Territories
- Construction start
- Jun 1, 2016(actual)
- Construction end
- Oct 18, 2018(actual)
Against the original forecast
- Construction start3 weeks lateforecast May 13, 2016