Fort Smith Road Upgrade
Fort Smith, Northwest Territories
Federal contribution
$3.4M
$3,387,709
Federal share67%
of $5.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 23, 2021
2022
Built
Approved 2 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Fort Smith
- Construction start
- May 1, 2022(actual)
- Construction end
- Oct 30, 2022(actual)
Against the original forecast
- Construction start4 weeks lateforecast Apr 1, 2022
- Construction end22 months earlyforecast Sep 1, 2024
Also in Fort Smith
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60219 in the federal list. How to read these figures.