Recreation and Community Centre Renovations

Fort Smith, Northwest Territories

completeRecreationSCF
Federal contribution
$2.5M
$2,479,000
Federal share71%

of $3.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 27, 2017
201720182019202020212022
Built

Approved 6 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Fort Smith
Construction start
Sep 30, 2020(actual)
Construction end
Feb 2, 2022(actual)

Against the original forecast

  • Construction end13 months lateforecast Dec 31, 2020

Also in Fort Smith

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47761 in the federal list. How to read these figures.