Road Upgrading and Paving - Seymour's Road, Cemetery Road and Mint Cove Pond Road North and South
Spaniard's Bay, Newfoundland and Labrador
Federal contribution
$162,759
Federal share29%
of $559.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 16, 2016
20172018
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Spaniards Bay
- Construction start
- May 8, 2017(actual)
- Construction end
- Aug 31, 2018(actual)
Against the original forecast
- Construction start5 weeks lateforecast Apr 1, 2017
- Construction end9 months earlyforecast May 30, 2019
Also in Spaniard's Bay
- Sewer Outfall from North Cove Outfall to Big Pond / Sewer Main Upgrade, Phase 2 and Sewage Pumping Station Upgrades$728.4K
- Road Reconstruction and Paving - Rectory Avenue/Casey's Lane$420.3K
- Pondside Road Upgrading and Paving$228.0K
- 2018 Road Upgrading and Paving - Mint Cove Pond Road North$116.7K
- Road Upgrading and Paving - Brown's Road$67.9K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46750 in the federal list. How to read these figures.