2018 Road Upgrading and Paving - Mint Cove Pond Road North

Spaniard's Bay, Newfoundland and Labrador

completeHighways and RoadsRNIS
Federal contribution
$116,713
Federal share28%

of $422.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
20202021
Built

Approved 3 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Spaniard’s Bay
Construction start
Sep 8, 2020(actual)
Construction end
Mar 24, 2021(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 1, 2020
  • Construction end5 months earlyforecast Aug 31, 2021

Also in Spaniard's Bay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53889 in the federal list. How to read these figures.