Schedule

Announced and approvedAug 6, 2018
20192020
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Spaniard’s Bay
Construction start
Aug 12, 2019(actual)
Construction end
Nov 6, 2020(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jul 1, 2019
  • Construction end13 months earlyforecast Nov 30, 2021