Paving Program

Meadows, Newfoundland and Labrador

completeHighways and RoadsSCF
Federal contribution
$43,268
Federal share16%

of $272.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 16, 2016
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Meadows
Construction start
Nov 12, 2016(actual)
Construction end
Nov 22, 2016(actual)

Against the original forecast

  • Construction start2 months lateforecast Sep 1, 2016
  • Construction end3 weeks lateforecast Nov 1, 2016

Also in Meadows

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46754 in the federal list. How to read these figures.