Multi-Purpose Court (Rink) Upgrades - Roof Installation
Meadows, Newfoundland and Labrador
Federal contribution
$172,174
Federal share29%
of $598.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 1, 2017
20182019
Built
Approved 2 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Meadows
- Construction start
- May 1, 2019(actual)
- Construction end
- Aug 23, 2019(actual)
Against the original forecast
- Construction start2 weeks earlyforecast May 15, 2019
- Construction end8 weeks earlyforecast Oct 15, 2019
Also in Meadows
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51662 in the federal list. How to read these figures.