Meadow Crescent Lift Station Replacement

Meadows, Newfoundland and Labrador

underwayWastewaterGIS
Federal contribution
$145,094
Federal share40%

of $362.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 21, 2025
202320242025
BuiltForecast

Approved 2.5 years before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Meadows
Construction start
Mar 31, 2025(actual)
Construction end
Oct 31, 2025(forecast)

Against the original forecast

  • Construction start4 months lateforecast Nov 29, 2024