MV Sound of Islay Rehabilitation
Clarenville, Newfoundland and Labrador
Federal contribution
$1.6M
$1,608,150
Federal share27%
of $6.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 31, 2017
2017
Built
Approved 6 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Construction start
- Feb 2, 2017(actual)
- Construction end
- Aug 31, 2017(actual)
Against the original forecast
- Construction start7 months lateforecast Jul 1, 2016
- Construction end8 months lateforecast Dec 31, 2016
Also in Clarenville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46768 in the federal list. How to read these figures.