Upgrades at the Dr. G. B. Cross Memorial Hospital

Clarenville, Newfoundland and Labrador

completeVentilationCVRIS
Federal contribution
$680,000
Federal share80%

of $850.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 28, 2024
202220232024
Built

Approved 3 years before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Nov 1, 2021(actual)
Construction end
Dec 15, 2023(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Oct 1, 2021
  • Construction end9 months lateforecast Mar 1, 2023

Also in Clarenville