Shoal Harbour Causeway Bridge Replacement
Clarenville, Newfoundland and Labrador
Federal contribution
$1.2M
$1,166,498
Federal share33%
of $3.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 28, 2022
202220232024
Built
Approved 7 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Clarenville
- Construction start
- Apr 11, 2023(actual)
- Construction end
- Dec 7, 2023(actual)
Against the original forecast
- Construction end7 months earlyforecast Jun 30, 2024