Hwy 417 (Ottawa Queensway) from Maitland Avenue to Island Park Drive Expansion

Ottawa, Ontario

completeHighways and RoadsMIC
Federal contribution
$37.7M
$37,704,683
Federal share50%

of $75.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 19, 2016
20172018201920202021
Built

Approved 8 weeks before the announcement.

Program
Building Canada Fund - Major Infrastructure Component
Construction start
Aug 1, 2017(actual)
Construction end
Jun 28, 2021(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 1, 2017
  • Construction end7 months lateforecast Nov 30, 2020

Also in Ottawa

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46769 in the federal list. How to read these figures.