Mayo Reservoir and Treatment Plant Upgrade
Federal contribution
$2.3M
$2,255,812
Federal share70%
of $3.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2016
201720182019
Built
Approved 5 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Village of Mayo
- Construction start
- Aug 16, 2016(actual)
- Construction end
- Aug 9, 2019(actual)
Against the original forecast
- Construction start2 weeks lateforecast Aug 1, 2016
- Construction end8 months lateforecast Dec 21, 2018
Also in Mayo