Kraft Creek Bridge Replacement

Timmins, Ontario

completeHighways and RoadsSCF
Federal contribution
$1.4M
$1,415,989
Federal share31%

of $4.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 7, 2016
201720182019
Built

Approved 7 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Timmins
Construction start
Jun 28, 2018(actual)
Construction end
Feb 14, 2019(actual)

Against the original forecast

  • Construction end5 months lateforecast Sep 21, 2018