Kraft Creek Bridge Replacement
Federal contribution
$1.4M
$1,415,989
Federal share31%
of $4.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 7, 2016
201720182019
Built
Approved 7 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Timmins
- Construction start
- Jun 28, 2018(actual)
- Construction end
- Feb 14, 2019(actual)
Against the original forecast
- Construction end5 months lateforecast Sep 21, 2018
Also in Timmins
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46876 in the federal list. How to read these figures.