Back to projects

Multimodal station amenities

Vancouver, British Columbia

completePublic TransitPTIF
Federal contribution
$2.0M
$2,000,000
Federal share50%

of $4.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 16, 2016
2017201820192020
Built
Program
Public Transit Infrastructure Fund
Ultimate recipient
Metro Vancouver
Construction start
Aug 17, 2017(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start5 months lateforecast Mar 31, 2017
  • Construction end3 months lateforecast Dec 31, 2019

Also in Vancouver

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46930 in the federal list. How to read these figures.