Mayo River Bridge Refurbishment

Mayo, Yukon

completeHighways and RoadsSCF
Federal contribution
$387,993
Federal share75%

of $517.3K total eligible cost; the rest comes from other partners.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Village of Mayo
Construction start
Sep 1, 2016(actual)
Construction end
Sep 28, 2016(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Aug 1, 2016
  • Construction end4 weeks lateforecast Sep 2, 2016