Water Line Bypass Caribou Road

Channel-Port aux Basques, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$124,349
Federal share42%

of $296.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
2017
Built
Program
Clean Water and Wastewater Fund
Construction start
Jun 1, 2017(actual)
Construction end
Oct 13, 2017(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 1, 2017
  • Construction end3 weeks earlyforecast Oct 31, 2017