New Chlorine Booster Station

Heart's Content, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$73,749
Federal share49%

of $150.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Heart’s Content
Construction start
Sep 25, 2017(actual)
Construction end
Jan 5, 2018(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Aug 1, 2017
  • Construction end7 weeks lateforecast Nov 15, 2017