Screen Chamber and Intake Upgrading Southern Cove Pond Intake, Cove Road
Heart's Content, Newfoundland and Labrador
Federal contribution
$78,134
Federal share45%
of $174.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Hearts Content
- Construction start
- Oct 13, 2017(actual)
- Construction end
- Jun 19, 2018(actual)
Against the original forecast
- Construction start16 months lateforecast Jun 1, 2016
- Construction end3 months earlyforecast Sep 30, 2018
Also in Heart's Content