Screen Chamber and Intake Upgrading – Southern Cove Pond Intake, Cove Road

Heart's Content, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$78,134
Federal share45%

of $174.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Heart’s Content
Construction start
Oct 13, 2017(actual)
Construction end
Jun 19, 2018(actual)

Against the original forecast

  • Construction start16 months lateforecast Jun 1, 2016
  • Construction end3 months earlyforecast Sep 30, 2018