Water Intake Upgrading Maloney's River

Harbour Main-Chapel's Cove-Lakeview, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$81,214
Federal share44%

of $185.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
2017
Built
Program
Clean Water and Wastewater Fund
Construction start
Sep 11, 2017(actual)
Construction end
Nov 30, 2017(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jul 31, 2017
  • Construction end4 months earlyforecast Mar 31, 2018