Water Intake Upgrading Maloney's River
Harbour Main-Chapel's Cove-Lakeview, Newfoundland and Labrador
Federal contribution
$81,214
Federal share44%
of $185.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
2017
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Harbour Main - Chapels Cove - Lakeview
- Construction start
- Sep 11, 2017(actual)
- Construction end
- Nov 30, 2017(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jul 31, 2017
- Construction end4 months earlyforecast Mar 31, 2018
Also in Harbour Main-Chapel's Cove-Lakeview
- Upgrading and Repaving Sections of Route 60 from Colliers Toward Harbour Main$1.5M
- Water and Sewer Upgrading Chapel's Cove & Fewer's Hill & Water Main Upgrades Conrans Road$453.8K
- Chapel's Cove Breakwater - Mitigation$397.8K
- Conran's Road Water Main Upgrades Phase II$244.2K
- 2022 Booster Pump Station for Water System Improvement, Harbour Drive$129.5K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47024 in the federal list. How to read these figures.