St. John's, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$2.7M
$2,720,504
Federal share50%

of $5.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
2017201820192020
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of St. John's
Construction start
Jun 20, 2017(actual)
Construction end
Dec 31, 2019(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jun 1, 2017
  • Construction end3 months earlyforecast Mar 31, 2020